Case No. 2011-0767 In the Matter of the Application of Duke Energy Ohio, Inc. to Establish and Adjust the Initial Level of its Distribution Reliability Rider

 

Date

02-07-2012

Duration

00:39:21

Download

Download File : 360p
 
 
Set In Point : sec Set Out Point : sec
Width : px Height : px
Code :
 Facebook Embed : To embed this video into your Facebook page, copy and paste the above URL into Facebook's 'Link' box in its 'Share' options.
Please Note : End points and dimensions are not recognized by Facebook.
Set In Point : sec Set Out Point : sec
URL :
 
Did PUCO Act Unreasonably in Reducing Utility's Claims For Costs of Restoring Power After 2008 Wind Storm?

In the Matter of the Application of Duke Energy Ohio, Inc. to Establish and Adjust the Initial Level of its Distribution Reliability Rider, Case no. 2011-0767
Appeal from Order of Public Utilities Commission of Ohio

ISSUE: Did the Public Utilities Commission of Ohio (PUCO) act unreasonably or contrary to law when it denied parts of an application by Duke Energy Ohio to recover through customer surcharges for the company’s claimed costs of restoring electricity in its service area in the aftermath of a September 2008 windstorm?
 
 
TimeTitle
00:00:40Amy B. Spiller for Duke Energy Ohio
00:20:03Stephen A. Reilly for the Public Utilities Commission of Ohio
00:37:30Summation: Amy B. Spiller for Duke Energy Ohio