Case No. 2010-1554 In the Matter of the Application of Buckeye Wind LLC for a Certificate to Construct Wind-Powered Electric Generation Facilities in Champaign County, Ohio

 

Date

09-21-2011

Duration

00:48:24

Download

Download File : 360p
 
 
Set In Point : sec Set Out Point : sec
Width : px Height : px
Code :
 Facebook Embed : To embed this video into your Facebook page, copy and paste the above URL into Facebook's 'Link' box in its 'Share' options.
Please Note : End points and dimensions are not recognized by Facebook.
Set In Point : sec Set Out Point : sec
URL :
 
Did State Power Siting Board Err in Approving Plans for Champaign County Wind Farm?

Neighboring Land Owners, County Officials Challenge Board’s Rulings

In the Matter of the Application of Buckeye Wind LLC for a Certificate to Construct Wind-Powered Electric Generation Facilities in Champaign County, Ohio, Case no. 2010-1554
Appeal from Decision of the Ohio Power Siting Board

ISSUE: Did the Ohio Power Siting Board act unreasonably or unlawfully in approving an application by Buckeye Wind LLC for construction of the state’s first large-scale wind-powered electric generating facility?
 
 
TimeTitle
00:01:02Jack A. Van Kley, for Union Neighbors United
00:13:44William L. Wright, for the Ohio Power Siting Board
00:29:38M. Howard Petricoff, for the Buckeye Wind Farm, LLC
00:38:50Summation: Jack A. Van Kley, for Union Neighbors United